Skip to main content

Quito Playground Renovation

The FY 2024-2025 Capital Improvement Projects Budget allocated $400,000 for the replacement of playgrounds, and Quito Park has been identified as a priority due to the age and condition of the equipment, last replaced in 1996. The District has two options being presented for Quito Park.

Scope of Work

 The board was presented two playground options. Option was approved not to exceed $74,301.92 (equipment) / $114,960.00 (demo and installation).

Total Cost of Equipment + Installation: $189,261.92

Playground Specs:

  • Recommended for ages 5-12
  • 16 Total Play Components / 8 elevated components
  • User Capacity: 75-85
  • 730 sq. ft. Pour-In-Place Surfacing
  • Swings: reflection selfie swing, tween mate swing, ADA swing
  • Medium Cosmos Jr. cable climber apparatus
Play & Park Structure Playground Approved by Board

 

 

Project Status

PhaseStart Date/MonthStatus
Scope of WorkOctoberBoard Approved 11.5.24
RFP 
Permits
Construction

 

Questions? 

Matt Parker, Parks Service Manager
mparker@pvrpd.org, 805.482.1996 x301