Lokker Park Playground Renovation 

Currently in Progress with Grand Opening on October 5, 2024.

We are currently renovating the Lokker Park playground based on community feedback, capital budget, and District Board of Directors approval.  

A flyer announcing the re-opening of Lokker Park Playground, with event details and amenities like refreshments, a ribbon-cutting, and games.

Project Status

PhasesDate (if applicable)Status
Community Kick Off MeetingJan. 13, 2024Completed
Conceptual Plan PresentationJan. 30, 2024Completed
Final Concept PresentationFeb. 13, 2024Completed
Final Concept Approved by Board of DirectorsMay 1, 2024Completed
Permits July 25, 2024Completed 
Demo (demo will be completed in phases) July 19, 2024 Completed
Build/ConstructionJuly 31 - CurrentIn progress
Completion & Grand Opening! Oct. 5, 2024

 

Design 

Playground Design Approved by Board of Directors on May 1

 

 

Project Photos (updated with progress)