Lokker Park Playground Renovation 

Currently in progress with an estimated completion date of October 2024.

We are currently renovating the Lokker Park playground based on community feedback, capital budget, and District Board of Directors approval.  

Project Status

PhasesDate (if applicable)Status
Community Kick Off MeetingJan. 13, 2024Completed
Conceptual Plan PresentationJan. 30, 2024Completed
Final Concept PresentationFeb. 13, 2024Completed
Final Concept Approved by Board of DirectorsMay 1, 2024Completed
Permits  Completed 
Demo (demo will be completed in phases) July 19 - CurrentIn progress
Build/ConstructionJuly 31 - CurrentIn progress

 

Design 

Playground Design Approved by Board of Directors on May 1

 

 

Project Photos (updated with progress)