Pleasant Valley Aquatic Center Roll-Up Doors
Completed January, 2026.
Installation of 2 motors powering roll-up doors at the Pleasant Valley Aquatic Center. District staff budgeted $45,000 for the completion of this project.
| Project Timeline | Start | End | Status |
|---|---|---|---|
| Define Scope of work | 7/8/2025 | 7/11/2025 | Completed |
| Informal Bid/Spec. Release: | 7/8/2025 | 7/11/2025 | Completed |
| Proposals/Quotes due: | 7/8/2025 | 7/18/2025 | Completed |
| Evaluation of Proposals: | 7/21/2025 | 7/26/2025 | Completed |
| Agreement Finalized | 8/26/2025 | 8/26/2025 | Completed |
| Project Start Date: | 12/22/2025 | 1/5/2026 | Completed |
| Marketing/Notice | 12/8/2025 | 1/5/2026 | Completed |
| Project Timeline Installation: | 12/22/2025 | 1/5/2026 | Completed |
| Project Completion Date: | 12/22/2025 | 1/5/2026 | Completed |