Pleasant Valley Aquatic Center Roll-Up Doors

A modern building surrounded by trees and greenery, featuring large windows and a sleek design under a clear blue sky.

Completed January, 2026.

Installation of 2 motors powering roll-up doors at the Pleasant Valley Aquatic Center. District staff budgeted $45,000 for the completion of this project. 

Project Timeline Start End Status
Define Scope of work 7/8/2025 7/11/2025 Completed
Informal Bid/Spec. Release: 7/8/2025 7/11/2025 Completed
Proposals/Quotes due: 7/8/2025 7/18/2025 Completed
Evaluation of Proposals: 7/21/2025 7/26/2025 Completed
Agreement Finalized 8/26/2025 8/26/2025 Completed
Project Start Date: 12/22/2025 1/5/2026 Completed
Marketing/Notice 12/8/2025 1/5/2026 Completed
Project Timeline Installation: 12/22/2025 1/5/2026 Completed
Project Completion Date: 12/22/2025 1/5/2026 Completed

 